OneStream Upgrade

Hi All,

For the folks that upgraded to v8 (preferably 8.4 or 8.5), I have few quick questions.

  1. How long it took for the whole process?
  2. Did you see the performance improvement?
  3. Did you require an extensive end-user testing?
  4. How was your overall experience with upgrade. Any lessons learned that you can pass on?

Thank you in advance for your time.

Cheers

PM

1 Reply

  • Hey Mikki​ ,

    Short answer to your first question that you probably already anticipated - "it depends".  Factors that can impact the upgrade process:

    • Version you are upgrading from
    • Extent of Solution Exchange solutions installed
    • Extent and complexity of business rules / dashboards in use
    • Span of integration points and types thereto (already on SIC, OIS or not, etc.)
    • Number of applications to migrated

    Non OneStream related factors:

    • IT standards and protocols to adhere to
    • Availability of resources (including BAU black out periods)
    • Org readiness - already have pre defined test plans, test scripts, resolution protocols, etc.
    • Degree of change management/ communications required

    Re: performance improvements - suggestions:

    • If performance improvements is something important, be sure to capture baseline metrics in the current environment (s) before the upgrade 
    • Common performance benchmark use cases include Month 12 Top Entity Force Consolidate, executing the slowest CubeView(s) and/or Dashboards(s), loading the longest running import job, retrieving the most common data pulls via Spreadsheet and Excel, -- essentially, focus on the area(s) that can have the greatest impact on user experience due to system performance deterioration
    • Recommend to do these "off hours" to minimize impact by other users

    Re: extent of user testing

    • Always helpful to involve your key power users and cover the most frequently used and critical functions in testing
    • Otherwise, eye of beholder.
    • The version you are upgrading from also dictates impact of visible change to users - Modern Browser Experience is automatically enabled after a certain version so can throw off users - should be proactively managed and eased in since the UI/UX is different (and is not yet at full parity with Windows App version)
    • Excel Add-In by and large need to match platform version but you can't have two versions running concurrently on the same machine

    Overall XP:

    • OneStream upgrade team has been great and proactively helpful in all the times we have gone through the bigger upgrades so far (e.g., pre 8.2 to 8.2+) - almost feels like a workout routine at this point for my team 😊

    Lessons learned:

    • Always plan ahead and engage OneStream team sooner to map our the upgrade plan that best suits your circumstances - but also remember you have tasks outside of their lists that only you / your org will know and can do.
    • Anticipate it will take longer than planned
    • Ensure a clear rollback strategy is in place and agreed upon by all stakeholders (e.g., in the remote chance that critical showstoppers cannot be resolved, you can defer final cutover)
    • Freeze all development during the upgrade if practical - remember that upgrade of your application(s) might happen twice - once at the start to assess impact and extent of post upgrade changes to be made, and another time towards cut over
    • Secure commitment (time and focus) from key resources - internal, OneStream, OneStream partner if applicable, etc 
    • Ensure there is adequate post upgrade end user support

     