Hi, Out of Curiosity,  Is it possible to update Task Activity.
  • sameburn's avatar
    sameburn
    24 days ago

    Hi

    You would use this BRApi to control the display of (a) the Task Activity Description and (b) the Percentage Complete value for the progress of a running task that is executed by Data Management through an Extender Business Rule or Data Management Workspace Service (we need to pass in ExtenderArgs).  

    Dim bValue As Boolean = BRApi.TaskActivity.UpdateRunningTaskActivityAndCheckIfCanceled(si, extenderArgs, activityDescription, percentCompleteToAdd)

    Updating the percentCompleteToAdd variable on the Task Activity window will only affect the Display and not make the process run more quickly. For Example, here I am able to control what gets displayed in the Task Progress window using this BRApi e.g.

    Hope this helps