I have my task manager set up by Weeks:
Therefore, I've been using Frequency ranges as 1-52 or 1,2,3 etc. as from the Task Manager guide. Let's say I want to make only 1 task group start on W1-W3. I input that into the task group and individual tasks but still it doesn't show up. However, if I don't put any frequency range, it shows up for all weeks I publish. I just want it to show up for 1 week.
BCA #1 doesn't show up at all in any charts but BCA #2 shows up in all weeks published.
I've also set up my Close Dates but it still doesn't work:
Any pointers or tips?