Nou1
14 days agoNew Contributor
Query to add a sequence for TASKs to run in Data Management so if one fails the others complete
we have a query where we have a list of Tasks that are running one after the other but are not linked, and if one of them fails for whatever reason, the rest of the tasks also stop running.
We have been informed by OS that this is not possible to configure this behaviour within the specific task or Data management so we can control which tasks stop and which ones need to be completed in case one of them fails.
We believe this makes sense to have a parameter / setting to set against each individual tasks if they just stop running or continue to completion in case of of the other tasks fail.
At the moment they all fail when there is an error.