Capital Planning FY change over issues

Ashlee
New Contributor III

Hello! We continue to run into below error when changing our Global POV (application properties) over to our new fiscal year 2025. When our global POV is set to 2025P1 we receive the below error. When our global POV stays on our last month's 2024P12 we do not get the below error. We feel like we've checked what we can in regards to the transformation rules, workflow profile settings, cube settings etc., and can not seem to correct this issue. Any suggestions are highly welcome. Thanks!

Ashlee_0-1726246589125.png

 

2 REPLIES 2

matt515
New Contributor III

Do you have one to one transformation rule for 2025M1 in the rule group? Was thinking maybe you had them entered in for prior periods but may need to add 2025M1, 2025M2, etc. in the one to one mappings.

Ashlee
New Contributor III

Hey Matt- We had built out our 2023 one to ones and never 2024 so we're assuming since 2024 was not needed that we wouldn't need 2025 either. I might test it out just to be sure.