Can I stop a Data Management if a Step Fails ??

Oscar
New Contributor III

Currently if a step fails the subsequent steps continue to execute

5 REPLIES 5

Mustafa_A
Contributor II

Are you running your DM step through Task Scheduler? 

I would suggest running it through TS and within it there is an option to disable the task (DM) if its fails.

Mustafa_A_0-1652368378443.png

 

Oscar
New Contributor III

I need to check that step 1 completed successfully before step 2 executes.

Cosimo
New Contributor III

I'm really hoping that the dev team considers adding pass/fail checks to Data Management sequences in the future. I use an Extender rule to perform step processing and check the return status of executed steps. 

Oscar
New Contributor III

that's exactly what i am trying to do ... I looked in golf stream for an example but i was not able to find one. I am building an extender to basically perform the steps below (import, validate, load) but need to validate each step completed successfully before executing the next. i wonder if there is an audit table that can be referenced ???

 

steps.png

TonyToniTone
Contributor

This would be a great enhancement Cosimo.  Let's get this on the Product radar.  Please submit a ticket to Support to get it to Triage and get it on the Product roadmap.  Thanks!