The OneStream Community is temporarily frozen until June 29th due to the ongoing maintenance. Please read the blog post here to learn more.
Forum Discussion
photon
9 months agoContributor
Process Cube automation
We have a business rule that, after loading data, runs a Process Cube.
When using this with the batch harvest API, it behaves pretty much as expected in that, after the process is complete, it retu...
ckattookaran
9 months agoValued Contributor
All those process return a task activity item which you can check for status. I would do it as a for loop to wait till the status becomes successful after the calc execution.
photon
9 months agoContributor
The network security is preventing me from uploading a screenshot but even Task Activity shows the "Process" completes in a fraction of a second but there's a calc running in a DM job for a full five minutes afterwards.
Related Content
- 12 days ago
- 2 years ago
- 3 years ago