Hi, has the task scheduler ever been fixed? So many issues because all the tasks are scheduled in UTC... If so which version?
Agree. I have the issue twice a year and here is how I currently resolve it. The morning after the time change I go into Task scheduler, open each recurring task that had a start date prior to the time change, change the start date to the current day and then save the task. It seems opening the task and updating the start date corrects it. Of course, it only works if you do it after the time change has occurred. Something I always look forward to doing twice a year :)
- nwillemse16 days agoNew Contributor
There are other issues with the schedular too. Try scheduling a job that runs every hour from 8am to 8pm CST. That won't run at all because 8pm is passed midnight UTC and the schedular is confused. Have to cut off the end time before midnight UTC and then schedule a different job for the hours after midnight. On top of that you need to schedule as Tuesday through Saturday to have it actually run on Mon-Fri 8pm...hopefully all these issues will be addressed.
Related Content
- 11 months ago
- 8 months ago
- 10 months ago