Is it possible to prevent a force consolidation to run on locked period ?

adoat
New Contributor III

Hi,

 

Without entering into the discussion of whether this is a best practice or not.

During some HFM replacement, we have seen occasionally that request being raised.

So, is it possible to prevent a force consolidation to run on locked entity / period whilst making it run for the unlocked ones ?

 

Aymar

1 ACCEPTED SOLUTION

adoat
New Contributor III

The Answer is Yes!

And has been partially answered here and there.

Thank you Christian for the nice posts I could find (see below for the links).

So in order to do so, you will actually have to first cancel the force consolidated.

Then by retrieving the period selected for the execution, you will be able to run through the entities and check wether they are locked or not.

If not, you will be able then to impact the calc status of the ones that aren't locked.

And eventually run a simple consolidation.

Be aware, this would only work if you run a force consolidate from the right click or a process step.

 

Hope this helps.

 

 

Kind regards,

 

 

Aymar

 

 

Namespace OneStream.BusinessRule.WcfEventHandler.WcfEventHandler
	Public Class MainClass
Public Function Main(ByVal si As SessionInfo, ByVal globals As BRGlobals, ByVal api As Object, ByVal args As WcfEventHandlerArgs) As Object
	Try
		Dim returnValue As Object = args.DefaultReturnValue
		args.UseReturnValueFromBusinessRule = True
		args.Cancel = False

		If args.IsBeforeEvent AndAlso args.WcfServiceType = WcfServiceType.Calculate AndAlso (args.OperationName="CalculateChartLogic" OrElse args.OperationName= "StartConsolidation" OrElse args.OperationName= "StartProcessCube") Then

			'Retrieve variable to pick up if consolidation is forced
			Dim povList As List(Of DataUnitPk) = args.inputs(1)
			Dim timeName As String = brapi.Finance.Members.GetMemberName(si, dimtypeid.Time, povList(0).TimeId)
			Dim isForced As Boolean = args.inputs(2)
			Dim isLogged As Boolean = args.inputs(3)

			If isForced Then
				'If it is forced then we cancel the force consolidation
				args.Cancel = True

				Dim cubeName As String = brapi.Finance.Cubes.GetCubeInfo(si, povlist(0).CubeId).Cube.Name			
				Dim scenarioName As String = BRApi.Finance.Members.GetMemberName(si, dimtypeid.Scenario, povList(0).ScenarioId)
				Dim entityName As String = BRApi.Finance.Members.GetMemberName(si, dimtypeid.Entity, povList(0).EntityId)
				Dim parentName As String = BRApi.Finance.Members.GetMemberName(si, dimtypeid.Entity, povList(0).ParentId)
				Dim currentMonth As Integer = BRApi.Finance.Time.GetPeriodNumFromId(si,povList(0).TimeId)
				
				'We retrieve the dimension name to make the rule multi cube ready
				Dim dimName As String = BRApi.Finance.Dim.GetDim(si, New DimPk(dimtypeid.Entity, BRApi.Finance.Members.GetDimIdFromMemberId(si, dimTypeId.Entity, povList(0).ParentId))).Name
				Dim timeId As Integer = BRApi.Finance.Time.GetFirstPeriodInYear(si,povList(0).TimeId)
				Dim lockedStatus As Boolean = False
				'For every entity under the parent being consolidate
				For Each entMember As Member In brapi.Finance.Members.GetBaseMembers(si, brapi.Finance.Dim.GetDimPk(si, dimName), povList(0).EntityId)
					'For every periods before the periode selected for the force consolidate, starting with the first period of the year
					For i = 1 To currentMonth
					
						
						Dim wfUnitClusterPK As WorkflowUnitClusterPk = BRApi.Workflow.General.GetInputWorkflowUnitClusterPkForMembers(si, povList(0).CubeId, povList(0).EntityId, povList(0).ScenarioId, timeId)
						lockedStatus = BRApi.Workflow.Status.GetWorkflowStatus(si, wfUnitClusterPK).Locked
'						brapi.ErrorLog.LogMessage(si, $"{cubeName}, {entMember.Name}, {parentName}, Local, {scenarioName}, {timeId}")

						'If the workflow is locked for this specific period
						If Not lockedStatus Then 

							'We impact the calcstatus
							Brapi.Finance.Data.ImpactCalcStatus(si, cubeName, entMember.Name, parentName, "Local", scenarioName, BRApi.Finance.Time.GetNameFromId(si,timeId))

'							Brapi.ErrorLog.LogMessage(si, "Locked Status = " & lockedStatus & $"{cubeName}, {entMember.Name}, {parentName}, Local, {scenarioName}, {timeName2}")
						End If
						
						'Next period
						timeId=BRApi.Finance.Time.GetNextPeriod(si,timeId,False)
					Next
				Next
				
			
				Dim parameters As New Dictionary(Of String, String) From {  {"wfcCube", cubeName},
	                                                                    {"wfcScenario", scenarioName},
	                                                                    {"wfcTime", timeName},
	                                                                    {"wfcEntity", entityName}}
				'We trigger a normal consolidation that will run on all impacted entities	
				brapi.Utilities.StartDataMgmtSequence(si, "BR_RunConsolidation", parameters)
					
			End If	

		End If

		Return returnValue
	Catch ex As Exception
		Throw ErrorHandler.LogWrite(si, New XFException(si, ex))
	End Try
End Function
	End Class
End Namespace

 

 

 

The associated data management should look like this :

 

adoat_0-1648721705100.png

 

Don't forget to create the associated literal parameter in a dashboard unit in order for this to work.

 

Related resources :

https://community.onestreamsoftware.com/t5/Internal-Consultants-PIE/Force-consolidate-only-runs-for-...

https://community.onestreamsoftware.com/t5/Internal-Consultants-PIE/Retrieving-the-isLocked-property...

 

View solution in original post

1 REPLY 1

adoat
New Contributor III

The Answer is Yes!

And has been partially answered here and there.

Thank you Christian for the nice posts I could find (see below for the links).

So in order to do so, you will actually have to first cancel the force consolidated.

Then by retrieving the period selected for the execution, you will be able to run through the entities and check wether they are locked or not.

If not, you will be able then to impact the calc status of the ones that aren't locked.

And eventually run a simple consolidation.

Be aware, this would only work if you run a force consolidate from the right click or a process step.

 

Hope this helps.

 

 

Kind regards,

 

 

Aymar

 

 

Namespace OneStream.BusinessRule.WcfEventHandler.WcfEventHandler
	Public Class MainClass
Public Function Main(ByVal si As SessionInfo, ByVal globals As BRGlobals, ByVal api As Object, ByVal args As WcfEventHandlerArgs) As Object
	Try
		Dim returnValue As Object = args.DefaultReturnValue
		args.UseReturnValueFromBusinessRule = True
		args.Cancel = False

		If args.IsBeforeEvent AndAlso args.WcfServiceType = WcfServiceType.Calculate AndAlso (args.OperationName="CalculateChartLogic" OrElse args.OperationName= "StartConsolidation" OrElse args.OperationName= "StartProcessCube") Then

			'Retrieve variable to pick up if consolidation is forced
			Dim povList As List(Of DataUnitPk) = args.inputs(1)
			Dim timeName As String = brapi.Finance.Members.GetMemberName(si, dimtypeid.Time, povList(0).TimeId)
			Dim isForced As Boolean = args.inputs(2)
			Dim isLogged As Boolean = args.inputs(3)

			If isForced Then
				'If it is forced then we cancel the force consolidation
				args.Cancel = True

				Dim cubeName As String = brapi.Finance.Cubes.GetCubeInfo(si, povlist(0).CubeId).Cube.Name			
				Dim scenarioName As String = BRApi.Finance.Members.GetMemberName(si, dimtypeid.Scenario, povList(0).ScenarioId)
				Dim entityName As String = BRApi.Finance.Members.GetMemberName(si, dimtypeid.Entity, povList(0).EntityId)
				Dim parentName As String = BRApi.Finance.Members.GetMemberName(si, dimtypeid.Entity, povList(0).ParentId)
				Dim currentMonth As Integer = BRApi.Finance.Time.GetPeriodNumFromId(si,povList(0).TimeId)
				
				'We retrieve the dimension name to make the rule multi cube ready
				Dim dimName As String = BRApi.Finance.Dim.GetDim(si, New DimPk(dimtypeid.Entity, BRApi.Finance.Members.GetDimIdFromMemberId(si, dimTypeId.Entity, povList(0).ParentId))).Name
				Dim timeId As Integer = BRApi.Finance.Time.GetFirstPeriodInYear(si,povList(0).TimeId)
				Dim lockedStatus As Boolean = False
				'For every entity under the parent being consolidate
				For Each entMember As Member In brapi.Finance.Members.GetBaseMembers(si, brapi.Finance.Dim.GetDimPk(si, dimName), povList(0).EntityId)
					'For every periods before the periode selected for the force consolidate, starting with the first period of the year
					For i = 1 To currentMonth
					
						
						Dim wfUnitClusterPK As WorkflowUnitClusterPk = BRApi.Workflow.General.GetInputWorkflowUnitClusterPkForMembers(si, povList(0).CubeId, povList(0).EntityId, povList(0).ScenarioId, timeId)
						lockedStatus = BRApi.Workflow.Status.GetWorkflowStatus(si, wfUnitClusterPK).Locked
'						brapi.ErrorLog.LogMessage(si, $"{cubeName}, {entMember.Name}, {parentName}, Local, {scenarioName}, {timeId}")

						'If the workflow is locked for this specific period
						If Not lockedStatus Then 

							'We impact the calcstatus
							Brapi.Finance.Data.ImpactCalcStatus(si, cubeName, entMember.Name, parentName, "Local", scenarioName, BRApi.Finance.Time.GetNameFromId(si,timeId))

'							Brapi.ErrorLog.LogMessage(si, "Locked Status = " & lockedStatus & $"{cubeName}, {entMember.Name}, {parentName}, Local, {scenarioName}, {timeName2}")
						End If
						
						'Next period
						timeId=BRApi.Finance.Time.GetNextPeriod(si,timeId,False)
					Next
				Next
				
			
				Dim parameters As New Dictionary(Of String, String) From {  {"wfcCube", cubeName},
	                                                                    {"wfcScenario", scenarioName},
	                                                                    {"wfcTime", timeName},
	                                                                    {"wfcEntity", entityName}}
				'We trigger a normal consolidation that will run on all impacted entities	
				brapi.Utilities.StartDataMgmtSequence(si, "BR_RunConsolidation", parameters)
					
			End If	

		End If

		Return returnValue
	Catch ex As Exception
		Throw ErrorHandler.LogWrite(si, New XFException(si, ex))
	End Try
End Function
	End Class
End Namespace

 

 

 

The associated data management should look like this :

 

adoat_0-1648721705100.png

 

Don't forget to create the associated literal parameter in a dashboard unit in order for this to work.

 